黑料新闻

漏 2025 黑料新闻

FCC Public Inspection Files:
路 路 路
路 路 路
Public Files ContactATSC 3.0 FAQ
Play Live Radio
Next Up:
0:00
0:00
0:00 0:00
Available On Air Stations

Delays continue and costs grow for MDC's massive underground tunnel project in Hartford

FILE: James Reves walks through the muck and flowing water back to the launch area at the MDC tunnel project, which will be a 4 miles, currently being dug under Hartford and West Hartford to manage storm water in Hartford, 黑料新闻 July 29, 2021.
Joe Amon
/
黑料新闻
FILE: James Reves walks through the muck and flowing water back to the launch area at the MDC tunnel project, which will be a 4 miles, currently being dug under Hartford and West Hartford to manage storm water in Hartford, 黑料新闻 July 29, 2021.

A legal dispute surrounding a massive 4-mile tunnel burrowed underneath Hartford and parts of West Hartford has been resolved. The Metropolitan District Commission (MDC) says it settled over $50 million in claims with a contractor who worked 200 feet underground to dig the project.

At issue were engineering reports submitted by MDC to its contractor 鈥 Kenny Obayashi, a joint venture (KOJV). Those documents, which included construction drawings and 鈥済eotechnical鈥 reports, served as the basis for the contractor鈥檚 initial $279.4 million project bid.

In a court complaint, KOJV said those reports failed to predict excessive amounts of groundwater that would later flow into the tunnel during the dig. The groundwater slowed the construction timeline and saddled the contractor with extra costs.

鈥淲hile work was proceeding in the initial reach of the Project tunnel, KOJV encountered water inflows that differed substantially and materially from what was indicated to bidders in the Contract Documents,鈥 the court complaint reads. 鈥淎s a result 鈥 KOJV incurred significant additional costs and its performance was delayed.鈥

The MDC says differing site conditions are not uncommon when constructing deep rock tunnels.

In an email, the agency says it 鈥渟aw merit鈥 in some of the contractor鈥檚 claims, but disagreed with other work change orders, which it said totaled over $100 million. The matter was referred to a federal court in Hartford in 2022. The case was dismissed when both parties reached an agreement in March.

鈥淯ltimately, the parties were able to resolve their differences by amending the total amount of all pending differing site condition change orders to approximately $51M,鈥 the MDC said in a statement.

A lawyer for KOJV did not immediately respond to a request for comment. The MDC says state officials reviewed and approved the excess costs.

When finished, the South Hartford Conveyance and Storage Tunnel will store up to 41 million gallons of wastewater that can be transported to an MDC plant for treatment.

Currently, such sewage overflows are sent untreated into the 黑料新闻 River during heavy rain.

Tunnel construction began in 2016. The project was initially expected to come online in 2023. The cost for the tunnel is now $335 million. The tunnel is not anticipated to be operational until fall of 2026, MDC says.

Other project costs connected to the tunnel include $115 million for a pump station that is under construction, $1.4 million in electrical upgrades and $38 million for New Britain Avenue conduits, according to the MDC.

Patrick Skahill is the assistant director of news and talk shows at 黑料新闻. He was the founding producer of 黑料新闻 Radio's The Colin McEnroe Show and a science and environment reporter for more than eight years.

Federal funding is gone.

Congress has eliminated all funding for public media.

That means $2.1 million per year that 黑料新闻 relied on to deliver you news, information, and entertainment programs you enjoyed is gone.

The future of public media is in your hands.

All donations are appreciated, but we ask in this moment you consider starting a monthly gift as a Sustainer to help replace what鈥檚 been lost.

SOMOS CONNECTICUT is an initiative from 黑料新闻, the state鈥檚 local NPR and PBS station, to elevate Latino stories and expand programming that uplifts and informs our Latino communities. Visit CTPublic.org/latino for more stories and resources. For updates, sign up for the SOMOS CONNECTICUT newsletter at ctpublic.org/newsletters.

SOMOS CONNECTICUT es una iniciativa de 黑料新闻, la emisora local de NPR y PBS del estado, que busca elevar nuestras historias latinas y expandir programaci贸n que alza y informa nuestras comunidades latinas locales. Visita CTPublic.org/latino para m谩s reportajes y recursos. Para noticias, suscr铆base a nuestro bolet铆n informativo en ctpublic.org/newsletters.

Federal funding is gone.

Congress has eliminated all funding for public media.

That means $2.1 million per year that 黑料新闻 relied on to deliver you news, information, and entertainment programs you enjoyed is gone.

The future of public media is in your hands.

All donations are appreciated, but we ask in this moment you consider starting a monthly gift as a Sustainer to help replace what鈥檚 been lost.

Related Content
黑料新闻鈥檚 journalism is made possible, in part by funding from Jeffrey Hoffman and Robert Jaeger.